The tender process is complete, and the contracts have been signed. Shovels are ready to go in the ground.
After this step, signage must be prepared and approved for the site. This will be displayed at the new building’s location so the public is aware of the construction and can anticipate the opening.
Construction rarely goes as planned. Many things can impact construction that affects the timelines, budget, and sometimes your patience. Some things to keep in mind include;
| Task | Dates |
|---|---|
| 1. Geotechnical Report 86 days | Tue 23‐10‐03 Thu 24‐02‐08 |
| 2. Survey Delivered 0 days | Wed 23‐10‐04 Wed 23‐10‐04 |
| 3. Tree Conservation Report 0 days | Mon 23‐10‐23 Mon 23‐10‐23 |
| 4. M&E, Structural, Civil Design Brief 0 days | Tue 23‐10‐17 Tue 23‐10‐17 |
| 5. Class D Estimate Update 17 days | Tue 23‐10‐17 Wed 23‐11‐08 |
| 6. Design Development 187 days | Mon 23‐08‐14 Tue 24‐05‐14 |
| 7. Design Meeting 0 days | Thu 23‐09‐21 Thu 23‐09‐21 |
| 8. Review Meeting 0 days | Mon 24‐01‐08 Mon 24‐01‐08 |
| 9. Review Meeting 0 days | Tue 24‐05‐14 Tue 24‐05‐14 |
| 10. Class C Estimate 15 days | Wed 24‐05‐15 Wed 24‐06‐05 |
| 11. Construction Documents (7 Months) 123 days | Thu 24‐02‐29 Fri 24‐08‐23 |
| 12. 33% Review 0 days | Tue 24‐05‐28 Tue 24‐05‐28 |
| 13. 66% Review 0 days | Fri 24‐06‐28 Fri 24‐06‐28 |
| 14. Class B Estimate 15 days | Fri 24‐06‐28 Fri 24‐07‐19 |
| 15. 99% Review 0 days | Thu 24‐08‐15 Thu 24‐08‐15 |
| 16. Building Permit Application 30 days | Fri 24‐06‐28 Mon 24‐08‐12 |
| 17. Bidding 27 days | Fri 24‐08‐23 Tue 24‐10‐01 |
| 18. Contract Administration (12 Months) 256 days | Wed 24‐10‐02 Tue 25‐10‐14 |
| 19. Post Construction 20 days | Wed 25‐10‐15 Tue 25‐11‐11 |